Cost Comparison

Steelforthepriceofwood.

LA framers are quoting $57 to $58/SF for wood. OFS steel is $58/SF installed and goes up in days, not months. Rough estimate. Final pricing comes after we review your plans.

Enter your project details to compare. Calculations update live.

Wood framing, installed$58/SF
$45/SF$70/SF

Use the installed $/SF from your wood framer's quote.

Square Footage

Total conditioned square footage

Site conditions
OFS Package

Rough estimate. Final pricing comes after we review your plans.

Engineering costs about the same for wood or steel. Use ours at $5/SF or bring your own engineer.

Wood Framing
Installed wood framing ($58/SF)$174,000
Total Upfront$174,000
Timeline
25 working days framing ((10 + 5 × 3,000 SF ÷ 1,000) × 1 complexity, rounded up)
OFS Steel Framing
Full service installed ($58/SF)$174,000
Total Upfront$174,000
Timeline
5 working days installation (3,000 SF ÷ 1,000 × 1.5, rounded up)
20 working days saved · 28 calendar days saved
Manufacturing Waste
<1% factory waste vs. 20%+ conventional
Total Advantage

Estimated net savings with OFS

$4,603
Upfront Difference
$0
Wood total − OFS total
Estimated builder's risk savings
$4,603
Builder's risk is priced by the month. Shorter frame time can lower it. Estimate only; your carrier sets the actual premium.
Schedule and builder's risk, how we got these numbers
Wood frame stage25 working days
(10 + 5 × 3,000 SF ÷ 1,000) × 1 complexity, rounded up to a whole day
OFS frame stage5 working days
3,000 SF ÷ 1,000 × 1.5 days per 1,000 SF, rounded up to a whole day
Working days saved20 days
25 wood days − 5 OFS days
Calendar days saved28 days
20 working days × 7 ÷ 5, rounded up
Home value (builder's risk exposure)$3,000,000
3,000 SF × $1,000 per SF
Estimated builder's risk savings$4,603
$3,000,000 × 2% × 28 calendar days ÷ 365

Builder's risk is priced by the month. Shorter frame time can lower it. Estimate only; your carrier sets the actual premium.

Estimates based on 2026 SoCal market benchmarks. Wood framing: installed $/SF from the slider. Wood frame days = (10 + 5 × SF ÷ 1,000) × complexity, rounded up; OFS install days = SF ÷ 1,000 × 1.5, rounded up; calendar days = working days × 7 ÷ 5, rounded up. Home value estimated at $1,000/SF for Los Angeles and the Palisades; builder's risk at 2% per year (4% in Very High Fire zones). Individual results vary. Consult a licensed contractor and your insurance provider for project-specific figures.