Rebuild Timeline: From Plans to a Standing Frame
A realistic look at how long each step takes when you frame with factory-built steel panels.
Time is money on a rebuild: rent, loan interest and insurance living-expense limits all run while you wait.
Typical steps
- Plan review (1 business day): send us your drawings and we review them.
- Priced proposal: you get a written scope and price.
- Engineering: we build a 3D steel model and coordinate stamped drawings. Timing depends on project size and your engineer of record.
- Permits: your jurisdiction reviews the plans. This is often the longest step and varies by city.
- Fabrication: our FRAMECAD F450 line roll-forms every stud and track and we assemble labeled panels.
- Delivery and install: panels arrive in install order. On many homes, the frame goes up in days rather than the weeks a stick-built frame can take.
What speeds things up
- Complete drawings when you first submit.
- Quick answers to our clarification questions.
- A foundation that's ready and inspected when panels arrive.
What we can't control
Permit review times and weather. We'll schedule fabrication around your permit date so panels don't sit.
Start the clock: submit your plans.